Eagles Landing Deck Addition 2
Landing deck addition.
BLOG
4th March, 2021 | user
Eagles Landing Deck Addition 2
Landing deck addition.
Mitchell Construction Services, LLC.
Douglasville, GA
Perform Schedule & Procurement Management for City of Atlanta Zone #3 Police Precinct. Render 2D & 3D modeling for residential remodel clients, this includes self-performing and subcontracting services for remodel construction and completion. Furnish & Installation of exterior deck & fence systems, exterior patio paver systems, and sliding glass door, barn door, and interior wood door systems.
North Point Hospitality Group Inc.
Atlanta, GA
Review RFP proposals from General Contractors and Vendors. Develop contracts for contractors & vendors, this includes negotiating costs and scopes of work, writing contracts, and ensuring all contractual obligations are adhered to. Review project schedules provided by GC, approve change requests provided by GC for changes in scope of work, and coordinate weekly meetings with design professionals and Contractors
W.G. Yates & Sons Construction
Atlanta, GA
Assisted in implementation of Yates & OSHA safety programs. Managed construction efforts to ensure the project is constructed in accordance with design, budget, and schedule, this included meeting with client, design representatives, subcontractors, city officials, etc. Developed trade partner contracts, this includes negotiating costs and scopes of work, writing contracts, and ensuring all contractual obligations are adhered to. Authorized and/or approved purchase requisitions (Purchase Orders). Performed weekly End of Job (EOJ) projections to track project cost, profits, and overall project completion, coordinated & Supervised weekly trade partner, LEAN/Pull Planning, BIM Coordination, and d eveloped & oversaw maintaining of contract documents including but not limited to production charts, RFI, submittal, drawing, buyout, and IOCC logs.
Engineering Consulting Services
Atlanta, GA
Performed in-place density testing using the Nuclear Test Method (ASTM D6938) or Drive, Tube Method (ASTM D2937), core sampling while performing air content, slump, compressive, and flexural strength tests of mortar, grout, and concrete. Assisted in laboratory testing of soil samples (Standard Proctor Method ASTM D698, Modified Proctor Method ASTM D1557) and Performed visual observation and inspection of soils, aggregates and structural steel placement.
Kiewit Power Constructors
Lenexa, KS
Learned the working aspects of power plants, transmission lines, and substations, worked with team members to prepare bid proposals for project owners ($75 million - $1 billion), assessed and analyzed drawings and technical specifications, and performed quantity / forecast take-offs to represent quantities and equipment needed to perform various job activities. Coordinated cost with local vendors for services involved in work activities. Used Google Earth Pro to determine access and logistics of projects. Used Microsoft Excel to develop linear schedule for projects and inputted unit rates, quantities, and equipment in estimating system for final proposal submittals
Rabren General Contractors
Auburn, AL
Assisted in site layout of Auburn University Recreation & Wellness Center ($40 million project), learned to use total station to shoot in concrete foundations, walls, columns, batter boards, forms etc. Used sight level to set 4 ft. benchmark on columns and slabs for reference. Set embed and anchor bolt templates and rods. Studied and analyzed architectural, civil, and structural drawings to determine scope of work. Worked and communicated effectively with Field Engineer, Superintendent, and Project Manager to ensure quality and accuracy of work performed